Bulk production is managed, not monitored. MakeMine issues the purchase order, holds the factory to the schedule at the milestone level, inspects during the run, and moves the goods through freight and customs to your door.

Book an Intro Call

You find out about the delay when you ask about it

The factory says in week six that everything is on track, and in week nine that the material arrived late. Both statements were true. Nobody was watching the milestone that mattered, components in house, which slipped in week two and quietly moved every date behind it.

A ship date is not a schedule. It is the last thing on one. Managing production means holding the milestones underneath it, catching the slip in the week it happens, and telling you the same day, not the week the goods were supposed to leave.

Workers assembling components along a production line at a partner factory

What production management covers

PO issuance

Purchase order written against the approved pre-production sample and the locked specification, with terms, dates, and tolerances defined in writing.

Material and component tracking

Fabric, hardware, containers, closures, and packaging confirmed in house at the factory before the run is scheduled.

Production scheduling

Your order slotted into the factory calendar with a start date, a run window, and a ship date.

Work in progress reporting

Milestone status against the schedule, visible in the MakeMine platform rather than requested by email.

In-process inspection

Quality checked during the run, not only at the end. See Quality & Compliance.

Freight and customs

Booking, documentation, classification, duty, and clearance. See Freight & Customs.

Delivery

To MakeMine fulfillment, to your 3PL, or direct to your warehouse.

The production sequence

Ten steps from an approved sample to goods on your dock, each one a milestone MakeMine holds the factory to.

  1. Pre-production approval

    Bulk cannot be scheduled until the pre-production sample or pilot batch is signed off

  2. PO issued

    Quantities, variants, price, ship date, and tolerance confirmed in writing

  3. Materials in house

    Components received and inspected at the factory before the run starts

  4. First article

    The first units off the line checked against the approved sample before the run continues

  5. Production run

    The line or batch runs, with in-process inspection throughout

  6. Top-of-production sample

    Pulled from the run and checked against the approved pre-production sample

  7. Finishing and pack-out

    Labeling, barcoding, and packing to your retail and warehouse spec

  8. Final inspection

    AQL inspection before the goods are released

  9. Freight and clearance

    Booking, documentation, duty, customs

  10. Delivery

    Received at your destination

Production lead times by category

Lead times run from pre-production approval to goods leaving the factory. Transit is separate. See Freight & Customs.

CategoryTypical lead time, approval to goods leaving the factoryWhat runs longest
Apparel45–70 daysFabric. Mill lead time and dye lot scheduling sit ahead of cutting and usually set the date
Accessories45–75 daysHardware and tooling. A custom buckle or mould has its own lead time before the run can start
Personal care6–10 weeks once formula and components are lockedComponentry. Filling is fast; the container, closure, and decoration are what the schedule waits on

For personal care the run itself is rarely the long pole. Formulation and twelve weeks of stability testing sit ahead of it. See Formulation.

What sets your minimum

Minimums are set by what goes into the product, not by the machine that assembles it. Almost every brand assumes the opposite.

ConstraintHow it works
Material or componentA mill's dye lot minimum, a jar mould's run size, or a hardware supplier's minimum sets the floor before the factory's own minimum applies. Usually the binding constraint
CountryThe largest single variable in apparel. China starts at 100 units per colorway; nearshore programs start in the thousands
Variant countEvery colorway, scent, shade, or size break carries its own setup and changeover, so splitting a SKU across variants raises the total
Process complexityTechnical construction and formulated products carry higher minimums than basics at the same facility
ToolingAnything requiring a mould, die, or plate carries a minimum set by amortising that tool across the run

Personal care minimums are on Personal Care Production.

How MakeMine handles the schedule

  • MakeMine budgets 60 days when the factory says 40.
  • We recommend the sourcing country that is the honest answer, even when a different one sounds better on paper.
  • If your launch date is not achievable, you hear it before the PO is issued, not after you have committed marketing spend.
  • If your volume is below the point where a factory relationship makes sense, we tell you that instead of quoting it anyway.
  • The factory making your product is disclosed to you rather than held as leverage, and you are welcome to join MakeMine on an on-site visit.

Frequently asked questions

What does a production manager actually do?

It is the work between an approved sample and delivered goods: issuing the purchase order against the locked specification, confirming materials are in house before the run is scheduled, tracking milestones rather than final dates, inspecting during the run, and moving the goods through freight and customs. The distinction that matters is milestone tracking. A partner watching only the ship date learns about a slip at the same time you do.

How long does production take?

Apparel runs 45 to 70 days from pre-production approval to goods leaving the factory. Personal care runs six to ten weeks once the formula and componentry are locked, though formulation and stability testing sit ahead of that. Transit is separate: five to ten days by ocean from Central America, 25 to 40 days from Asia. A first order from development to delivered goods is commonly four to seven months.

What is a minimum order quantity, and what sets it?

The MOQ is the smallest quantity a factory will run. It is usually set by what goes into the product rather than by the assembly itself. A mill's dye lot minimum, a container mould's run size, or a component supplier's own floor typically binds before the factory's does. Sourcing country is the other large variable: in apparel, China starts at 100 units per colorway while nearshore programs start in the thousands.

What happens if the factory misses the ship date?

MakeMine tracks milestones rather than final dates, so a slip surfaces at the milestone that caused it rather than at the end. You are notified the same day with the recovery options, whether that is air freight on a portion, a partial shipment, or a revised date, and the cost of each.

Can I visit the factory making my product?

Yes. MakeMine's factory network is disclosed to clients rather than held as leverage, and brands are welcome to join MakeMine on an on-site visit.

Does MakeMine manage production outside apparel?

Yes. MakeMine manages apparel, accessories, and personal care today, through a vetted factory network across China, Vietnam, South Korea, Honduras, and Peru, plus US contract manufacturers for personal care. The specification, the minimums, and the compliance requirements change by category. The management does not.

Who issues the purchase order, MakeMine or my brand?

MakeMine issues it to the factory, written against the approved pre-production sample and the locked specification, with quantities, price, ship date, and tolerance stated. Defining tolerance and rework responsibility on the PO is what keeps them from becoming a negotiation after goods are already made.

Managed, not monitored.